Infrastructure: water and sewer to the US 301 bypass
Agency: City of Starke. Status, in the Telegraph's words: the "Starke City Commission voted unanimously Sept. 3 to award a $5.86 million contract to extend water and sewer service to the U.S. 301 bypass."[1] The same report adds that it was "a project that came in less than half of what the city had budgeted for it."[1]
What to do with this: if you are pricing land along the bypass, ask the city which parcels the extension reaches and when service is expected, and for a parcel it does not reach, get the cost of wells, septic or a private extension before you make an offer. The public report covers the award, not the completion date.
Utility capital projects also came up in the city's budget talks: "Starke city officials spent nearly an hour Aug. 18 picking apart the numbers behind next year's utility budget," and "much of the conversation circled back to a handful of big-ticket capital projects."[2]
Infrastructure and public property: the Southside Elementary exchange
Agencies: Bradford County School Board and City of Starke. "The Bradford County School Board has signed off on a property swap with the city of Starke."[3] The deal would "send the former Southside Elementary School campus to the city and give the school district the city's maintenance and purchasing facility on North Orange Street."[3] Status and date: "The board approved the amended property exchange agreement Sept. 23."[3] The headline adds the caveat: "School board OKs land swap with Starke; timeline hinges on funding."[3]
What to do with this: if you own or are buying property near the former Southside Elementary campus or the North Orange Street facility, ask the city and the school district what each plans for its new site. The report does not say, so this page does not guess.
Private projects: Chick-fil-A site plan
The Telegraph's headline: "Chick-fil-A plan approved, work could begin by year's end." The report says the "plans for a Starke restaurant took a key step forward with the approval of its site plan Oct. 6."[4] On timing, "City Manager Drew Mullins said construction could start before the end of the year."[4]
What to do with this: if you lease or own retail space nearby, ask the city for the approved site plan to see the access points and parking, and treat one approval as a fact about this site, not a trend.
Private property: former gas station on State Road 100
Agency: City of Starke. "The Starke City Commission is nearing the end of a code enforcement case involving a vacant former gas station on State Road 100."[5] The report says the city attorney told commissioners "that the city has been cleared to move forward with taking ownership of the property."[5]
What to do with this: if you own property near the former gas station on State Road 100, ask the city what it plans for the site once it takes ownership. The report does not say.
City plans: Starke's 2026-27 budget
Agency: City of Starke. "Starke city commissioners adopted a tentative property tax rate and a $61 million budget for the 2026-27 fiscal year."[6] If a purchase depends on city services, read the final adopted budget, not the tentative one, for the capital items it funds.
City plans and county plans that cover Starke
Bradford County capital improvement plan. County commissioners were "presented a preliminary five-year capital improvement plan Aug. 4 calling for $28.89 million in road, facility, fleet and emergency equipment projects," covering spending "between the 2026-27 and 2030-31 fiscal years, with roughly three-quarters of that spending concentrated in the coming year."[7] The report calls the plan preliminary, and this page does not list which of its projects, if any, fall inside Starke; ask the county for the adopted plan.
Bradford County economic development strategic plan. "Bradford County commissioners got a detailed look at a new economic development strategic plan at their May 21 meeting," where "a senior planner and project manager with Halff Associates, presented the results of a state-funded Community Planning Technical Assistance grant."[8] The report describes it as "The $75,000 grant written in the summer of 2025." The report's headline: "Plan offers look at future fairgrounds, airport and bypass development."[8]
Our October 2026 research did not find a dated, public status for an update to the City of Starke comprehensive plan, so this page lists none. If you need the future land use for a specific parcel, ask the city's building and zoning office for the current map.
What this tracker does not cover
Bradford County approvals that their sources place near Lawtey or elsewhere in the county, rather than in Starke, are on the market outlook, not here. Residential subdivisions are left out unless they include commercial space. Items drop off this page when the record shows them finished or withdrawn.
Weighing land near the bypass or a site in Starke? Start with what the record shows.
Talk with MakaylaQuestions people ask
What development is underway in Starke, FL?
As of October 2026, the public record shows a $5.86 million contract awarded Sept. 3 to extend water and sewer to the US 301 bypass, a Chick-fil-A site plan approved Oct. 6, a school board property exchange with the city approved Sept. 23, and the city moving to take ownership of a vacant former gas station on State Road 100.
Is the Starke bypass getting water and sewer?
The Starke City Commission voted unanimously Sept. 3 to award a $5.86 million contract to extend water and sewer service to the US 301 bypass, according to the Bradford County Telegraph. The report covers the contract award, not a completion date.
When will Chick-fil-A in Starke start construction?
Its site plan was approved Oct. 6, and City Manager Drew Mullins said construction could start before the end of the year, according to the Bradford County Telegraph. Our October 2026 research did not find an opening date.
Where can I find Bradford County's capital improvement plan?
The county was presented a preliminary five-year plan on Aug. 4 calling for $28.89 million in road, facility, fleet and emergency equipment projects between the 2026-27 and 2030-31 fiscal years. Ask the county for the adopted version.
Sources
- Starke awards $5.86 million contract to extend water, sewer lines to bypass, Bradford County Telegraph, September 8, 2026. Accessed October 14, 2026.
- Starke officials talk projects during budget workshop, Bradford County Telegraph, August 25, 2026. Accessed October 14, 2026.
- School board OKs land swap with Starke; timeline hinges on funding, Bradford County Telegraph, September 30, 2026. Accessed October 14, 2026.
- Chick-fil-A plan approved, work could begin by year's end, Bradford County Telegraph, October 6, 2026. Accessed October 14, 2026.
- Starke moving to take ownership of blighted former gas station on State Road 100, Bradford County Telegraph, September 15, 2026. Accessed October 14, 2026.
- Starke commissioners field pointed budget criticism, adopt tentative $61 million spending plan, Bradford County Telegraph, September 8, 2026. Accessed October 14, 2026.
- Bradford County outlines $28.9 million five-year capital improvement plan, Bradford County Telegraph, August 11, 2026. Accessed October 14, 2026.